Application
36.—(1)  This Part applies to a case where —
(a)parties (none of whom is a prescribed person) entered into a contract (called in this Part the affected contract) that —
(i)falls within such description of contracts as may be prescribed;
(ii)is in force during the prescribed period (or any part of it); and
(iii)is, on or after 1 February 2020 and before the expiry of the prescribed period, affected in the prescribed manner by a delay in the performance by a party to a construction (or construction-related) contract or supply (or supply-related) contract, or a breach of such contract, where such delay or breach —
(A)occurs on or after 1 February 2020 and before the expiry of the prescribed period; and
(B)is to a material extent caused by a COVID-19 event; and
(b)other prescribed conditions are satisfied.
(2)  This Part does not apply to such circumstances as may be prescribed by regulations made under section 39.
[Act 30 of 2020 wef 30/09/2020]
(3)  In this section, “prescribed period” means a period prescribed under section 39 for the purposes of this Part.
[Act 37 of 2020 wef 18/11/2020]