Building Control (Temporary Buildings) Regulations 2018
Table of Contents
Enacting Formula
Part 1 PRELIMINARY
1 Citation and commencement
2 Definitions
3 Maximum period that temporary building is permitted to be used
4 Application
Part 2 TEMPORARY BUILDING PERMITS
5 Application of Part
6 Permission required to erect and use temporary building
7 Application for temporary building permit
8 Preliminary approval in respect of permit
9 Duties of professional engineer
10 Duties of builder
11 Grant of permit
12 Extension of permit
13 Lapsing of preliminary approval
14 Revocation of preliminary approval or permit
15 No refund of fees
16 Demolition of temporary building
Part 3 TEMPORARY BUILDINGS THAT DO NOT REQUIRE PERMIT
17 One-storey workers’ quarters or site offices, etc.
18 2-storey and 3-storey workers’ quarters, etc.
Part 4 MISCELLANEOUS
19 Protective structures required for temporary building works
20 Requirements relating to protective structures
21 General penalty