Notice on extension of delivery date not exceeding 122 days
8.—(1) A notice from the developer to the purchaser about the period of extension mentioned in section 39I(1) of the Act must —
(a)
be —
(i)
in the case of the first extension of the delivery date — in Form 1; and
(ii)
in the case of any subsequent extension of the delivery date — in Form 2; and
(b)
be served on the purchaser by a prescribed mode of service.
(2) For the purposes of section 39I(1)(b) of the Act, the prescribed time for the developer to notify the purchaser of the period of the extension is —
(a)
unless sub‑paragraph (b) applies — any time within the period of 28 days starting on 1 July 2021; and
(b)
if both the certificate of statutory completion and temporary occupation permit in respect of the housing accommodation or commercial property in question are issued or granted under section 12(1) or (3) of the Building Control Act 1989 on or after 1 July 2021, at any time —
(i)
on or after 1 July 2021; but
(ii)
before the expiry of a period of 28 days after the earlier of the following: