(a) | the plot is zoned “Residential” in the Master Plan; |
(b) | [Deleted by S 81/2024 wef 14/02/2024] |
(c) | no part of the plot consists of State land; |
(d) | the plot abuts a public road; |
(da) | no part of the plot is demarcated in any plan approved by the relevant authority for roads, streets, road reserves, road widening and drainage reserves or for any other public use; [S 81/2024 wef 14/02/2024] |
(e) | the operations will result in a landed dwelling-house of the same housing type as the existing or demolished landed dwelling-house, as the case may be; |
(ea) | the operations do not result in any change to the vehicular access arrangements of the plot; [S 81/2024 wef 14/02/2024] |
(f) | earthfill works on the plot, if any, will not cause the level of any point in the plot to be more than one metre above the lower of the following:(i) | the level of that point in the plot before the operations; or | (ii) | the level of any point at the abutting edge of abutting land; [S 273/2015 wef 11/05/2015] |
|
(fa) | [Deleted by S 81/2024 wef 14/02/2024] |
(fb) | [Deleted by S 81/2024 wef 14/02/2024] |
(g) | the operations comply with all the relevant planning guidelines, including guidelines on building setback, site coverage, housing type and building height issued by the competent authority or, if the operations do not comply with any requirement of the relevant planning guidelines, the qualified person for the operations has obtained a written waiver by the competent authority of that requirement in relation to those operations; [S 81/2024 wef 14/02/2024] |
(h) | the operations will result in a landed dwelling-house which stands on every lot within the plot; |
(i) | not more than one landed dwelling-house will exist on the plot when the operations are completed; |
(j) | no part of the existing landed dwelling-house comprises works that are unauthorised under the Act; |
(k) | a declaration is made by the qualified person for the operations in such form as the competent authority may require that —(i) | sub-paragraphs (a) to (da) and (j) have been complied with; [S 81/2024 wef 14/02/2024] | (ii) | the plans lodged with the competent authority under sub-paragraph (l) have been prepared in compliance with the relevant planning guidelines referred to in sub-paragraph (g) or, if the plans were not prepared in compliance with any requirement of such guidelines, the qualified person has obtained a written waiver by the competent authority of that requirement in relation to the plans; [S 195/2007 wef 07/05/2007] [S 81/2024 wef 14/02/2024] | (iia) | the qualified person has obtained the consent of the owner of the plot to the lodgment of the plans with the competent authority under sub-paragraph (l); [S 81/2024 wef 14/02/2024] | (iii) | the qualified person will ensure that the operations shall be carried out in compliance with sub-paragraph (n); and [S 195/2007 wef 07/05/2007] | (iv) | the operations are not excluded from the authorisation under paragraph 3 by reason of paragraph 5(1) or (2); [S 195/2007 wef 07/05/2007] |
|
(l) | prior to or together with the submission of any application to the Commissioner of Building Control for approval of the building plans for the operations under the Building Control Act 1989, the following are lodged with the competent authority at the same time together with the fee specified in sub-paragraph (2):(i) | the plans for the operations as required by the competent authority; | (ii) | the declaration required under sub-paragraph (k); and | (iii) | if applicable, the written waiver by the competent authority mentioned in sub-paragraph (g); [S 81/2024 wef 14/02/2024] |
[S 626/2022 wef 31/12/2021] [S 81/2024 wef 14/02/2024] |
(m) | [Deleted by S 81/2024 wef 14/02/2024] |
(n) | the operations are carried out in compliance with —(i) | sub-paragraphs (e), (ea), (f), (h) and (i); [S 273/2015 wef 11/05/2015] [S 81/2024 wef 14/02/2024] | (ii) | where the fee paid under sub-paragraph (l) is $700, the conditions in sub-paragraph (2)(a)(i) and (ii); [S 65/2015 wef 11/02/2015] [S 510/2016 wef 17/10/2016] [S 626/2022 wef 31/12/2021] [S 81/2024 wef 14/02/2024] | (iii) | the plans that are lodged with the competent authority under sub-paragraph (l) for such operations; and | (iv) | the requirements of all relevant authorities; and [S 65/2015 wef 11/02/2015] |
|
(o) | the authorisation has not lapsed under paragraph 5A(1). [S 65/2015 wef 11/02/2015] |