PART 3
POWERS OF AUTHORITY
Applicability of powers
15.—(1)  Regulations 16, 17 and 18 only apply in relation to a development within a railway corridor or railway protection zone if the Authority is of the opinion that the carrying out of the development or any engineering works under the development —
(a)is in contravention of —
(i)these Regulations; or
(ii)the code of practice mentioned in regulation 14;
(b)endangers or is likely to endanger the safety of any person travelling in or on the railway or railway premises;
(c)causes damage to or is likely to cause damage to the railway or railway premises; or
(d)disrupts or is likely to disrupt the operations of a rapid transit system.
(2)  In this Part, “specified person”, in relation to a development, means any of the following persons:
(a)the developer of the development;
(b)a person carrying out the development;
(c)a qualified person appointed under regulation 11(1) to supervise the development or the engineering works under the development, as the case may be.
Power to impose additional requirements
16.  Subject to regulation 15, the Authority may by written notice require one or more specified persons to —
(a)comply with any requirement that the Authority thinks fit to impose; and
(b)take any measures that may be necessary,
in relation to the development or any engineering works under the development, to prevent, stop or remedy any damage to a railway or railway premises.
Power to require stoppage of development
17.  Subject to regulation 15 and without affecting regulation 16, the Authority may, by written notice, require one or more specified persons to stop carrying out, or causing or permitting to be carried out the development or any engineering works under the development (in whole or in part) indefinitely or for any period specified by the Authority.
Power to require information on development
18.  Subject to regulation 15, the Authority may by written notice, require one or more specified persons to provide to the Authority, any specified information or document in respect of the development or any engineering works under the development, in the form and manner and within the time specified by the Authority.