2.—(1) In these Regulations, unless the context otherwise requires —“air-conditioning ducting installation” means the installation of air-conditioning ducting or any associated fittings, including thermal insulation, for the purposes of the cooling and mechanical ventilation of a building; [S 190/2011 wef 15/04/2011] |
“appropriate form”, in relation to any purpose for which a specific form is required to be used, means the relevant form that —(a) | is provided by the Authority and obtainable from the Building and Construction Authority Academy at 200, Braddell Road, Singapore 579700 during such hours as that office is open for business; or | (b) | is set out on the Authority’s Internet website http://www.bca.gov.sg/coretrade; [S 84/2012 wef 01/04/2012] |
|
“authorised officer”, in relation to any provision in these Regulations, means an employee of the Authority who is authorised in that behalf by the Authority for the purposes of that provision; |
“Building and Construction Authority Academy” means the educational and research institution established by the Authority known as the Building and Construction Authority Academy of the Built Environment; |
“building works” has the same meaning as in section 2(1) of the Building Control Act (Cap. 29); [S 84/2012 wef 01/04/2012] |
“certificate of registration” means any certificate of registration issued thereto under regulation 8(5) to any construction personnel; |
“cladding and curtain wall installation” means the installation of any external cladding or curtain wall, or any associated fittings, as the exterior covering or exterior wall of a building; [S 190/2011 wef 15/04/2011] |
“construction foreman” and “construction tradesman” have the same meanings, respectively, as in Part V of the Building Control (Licensing of Builders) Regulations 2008 (G.N. No. S 641/2008); |
“construction personnel” means a natural person who is —(a) | a construction supervisor of any class; | (b) | a construction foreman of any class; or | (c) | a construction tradesman of any class; [S 84/2012 wef 01/04/2012] |
|
“construction plant operation works” means operating any of the following plant or machinery:(a) | a saddle jib tower crane; | (b) | a luffing jib tower crane; | (c) | a mobile crane (truck mounted); | (d) | a crawler crane; | (e) | a hydraulic excavator; | (f) | a telescopic handler; | (g) | a bulldozer; | (h) | a track shovel; | (i) | an excavator loader; | (j) | a piling rig; | (k) | an underground pipe jacking machine; | (l) | a tunnel boring machine; | (m) | an asphalt concrete paver; | (n) | a crawler drill; [S 190/2011 wef 15/04/2011] |
|
“construction supervisor” has the same meaning as in section 29H(5) of the Building Control Act; [S 84/2012 wef 01/04/2012] |
“doors and windows installation” means the installation of any door, window panel or frame, or any associated fittings, for building works; [S 190/2011 wef 15/04/2011] |
“drywall installation” means the on-site fabrication, installation or erection of any drywall panel or any associated fittings in the interior of a building; [S 190/2011 wef 15/04/2011] |
“electrical works” means installing any wiring, cable, conduit, trunking, isolators, switch socket outlets, power switches or any other fittings for transmission of electricity for lighting, heating, cooling or other similar purposes in a building; |
“fire protection works” has the same meaning as in the Fire Safety Act (Cap. 109A); [S 190/2011 wef 15/04/2011] |
“gas pipefitting works” means the installation of any gas service pipe, pipe fitting, conveyance, valve, regulator or any associated device used or to be used for the control and use of gas in a building; [S 190/2011 wef 15/04/2011] |
“glazing works” means the installation of glass or any associated fittings in a building; [S 190/2011 wef 15/04/2011] |
“joinery works” means the on-site fabrication of fitments, fittings or any related carpentry works for the installation of timber furniture to the interior wall, floor or any other part of a building; [S 190/2011 wef 15/04/2011] |
“lift” has the same meaning as in the Building Maintenance and Strata Management (Lift and Building Maintenance) Regulations 2005 (G.N. No. S 194/2005); [S 190/2011 wef 15/04/2011] |
“lift installation” means installation of any lift; [S 190/2011 wef 15/04/2011] |
“mechanical and electrical works” —(a) | means any work performed or carried out to install any mechanical or electrical installation; and | (b) | includes the installing, constructing, erecting, repairing or the altering of the mechanical or electrical installation or the replacing of any part thereof or the adding of any part thereto or the carrying out of any work thereon for the maintenance thereof of such installation; but | (c) | does not include work in relation to the manufacturing of such installation; [S 84/2012 wef 01/04/2012] |
|
“plumbing and piping works” means installing any liquid, water or sanitary piping, or any associated fittings, including thermal insulation, for the conveyance of liquid, potable water distribution, or soil or waste water disposal in a building; [S 190/2011 wef 15/04/2011] |
“registered” means registered under these Regulations; |
“reinforced concrete works” means the on-site fabrication, installation or erection of formwork and steel reinforcement for reinforced concrete work, including —(a) | fabrication (both on-site or off-site) of pre‑cast concrete components; and | (b) | installation of pre-cast concrete components; [S 84/2012 wef 01/04/2012] |
|
“skills assessment” means an assessment conducted by or on behalf of the Authority of the skills in the class of work a construction tradesman or a construction foreman is or is to be registered in; |
“structural steel works” means the on-site fabrication, fitting, welding and erection of steel members or components to form an integral part of any structural system of a building; [S 190/2011 wef 15/04/2011] |
“structural works” has the same meaning as in section 2(1) of the Building Control Act; [S 84/2012 wef 01/04/2012] |
“suspended ceiling installation” means the installation of any false ceiling, ceiling board, panel, tile or frame, or any associated fittings, that is hung from the soffit of structural elements of a building; [S 190/2011 wef 15/04/2011] |
“test” means a test conducted by or on behalf of the Authority of the theoretical knowledge of a construction foreman and his communication skills; |
“tiling, stone laying and floor finishing works” means the laying of tiles, marble or stone finishes to any interior or exterior wall or any floor of a building, or timber finishes to any interior or exterior floor of a building; [S 190/2011 wef 15/04/2011] |
“waterproofing works” means applying or laying of material to waterproof any basement, foundation, roof, wet area or wall in the interior or on the exterior of a building. |
(2) All forms used for the purposes of these Regulations shall be completed in the English language and in accordance with such directions as may be specified in the form or by the Authority. |
|