Building and Construction Industry Security of Payment Act
(Chapter 30B, Section 41)
Building and Construction Industry Security of Payment Regulations
Rg 1
G.N. No. S 2/2005

REVISED EDITION 2006
(31st August 2006)
[1st April 2005]
Citation
1.  These Regulations may be cited as the Building and Construction Industry Security of Payment Regulations.
Definitions
2.  In these Regulations, unless the context otherwise requires —
“main contract” means a contract between an owner and any other person (not being a party to a sub-contract made under that contract) for the carrying out of construction work at or on, or for the supply of goods or services in relation to, a construction site by that other person;
“service address”, in relation to a person, means an address for the service of documents;
“sub-contract”, in relation to a construction site, means a contract for the carrying out of construction work at or on, or for the supply of goods or services in relation to, the construction site, other than the main contract.
Agreements excluded from definition of “supply contract”
3.  The definition of “supply contract” in section 2 of the Act does not include agreements which do not contain any provision specifying or identifying the construction site or the construction project in relation to which goods are to be supplied.
Contracts excluded from application of Act
4.  Any contract which satisfies the following conditions shall be excluded from the application of the Act:
(a)the contract is made, in writing, within a period not exceeding 6 months from 1st April 2005;
(b)the contract is a sub-contract made under a main contract; and
(c)the main contract is made before 1st April 2005.
Payment claims
5.—(1)  Where a contract does not contain any provision specifying the time at which a payment claim shall be served or by which such time may be determined, then a payment claim made under the contract shall be served by the last day of each month following the month in which the contract is made.
(2)  Every payment claim shall —
(a)be in writing;
(b)identify the contract to which the progress payment that is the subject of the payment claim relates; and
(c)contain details of the claimed amount, including —
(i)a breakdown of the items constituting the claimed amount;
(ii)a description of these items;
(iii)the quantity or quantum of each item; and
(iv)the calculations which show how the claimed amount is derived.
Payment responses in relation to construction contracts
6.—(1)  Every payment response provided in relation to a construction contract shall —
(a)be in writing;
(b)be addressed to the claimant;
(c)state “nil” where the respondent does not propose to pay any part of the claimed amount and the reasons therefor; and
(d)where the response amount is less than the claimed amount —
(i)contain the amount that the respondent proposes to pay for each item constituting the claimed amount, the reasons for the difference in any of the items and the calculations which show how the amount that the respondent proposes to pay is derived; and
(ii)contain any amount that is being withheld, the reason for doing so and the calculations which show how the amount being withheld is derived.
(2)  A payment response provided in relation to a construction contract may be varied only by notice in writing which satisfies the following requirements:
(a)the notice shall be addressed to the claimant;
(b)the notice shall identify the payment response being varied and state whether the variation would supersede or supplement the payment response;
(c)where the variation supersedes part of the payment response, the notice shall identify the part of the payment response that is superseded; and
(d)the variation shall conform with paragraph (1)(c) and (d) as appropriate.
Adjudication applications
7.—(1)  Every notice of intention to apply for adjudication shall contain the following particulars:
(a)the names and service addresses of the claimant and the respondent;
(b)the date of the notice;
(c)the particulars of the relevant contract, comprising —
(i)the project title or reference, or a brief description of the project;
(ii)the contract number or a brief description of the contract; and
(iii)the date the contract was made;
(d)the claimed amount;
(e)the response amount (if any); and
(f)a brief description of the payment claim dispute.
(2)  Every adjudication application shall —
(a)contain the names and service addresses of the claimant, the respondent, the principal (if known) and the owner concerned;
(b)state whether the relevant contract is a construction contract or a supply contract;
(c)contain the particulars of the relevant contract, comprising —
(i)the project title or reference, or a brief description of the project;
(ii)the contract number or a brief description of the contract; and
(iii)the date the contract was made;
(d)contain an extract of the terms or conditions of the contract that are relevant to the payment claim dispute; and
(e)be accompanied by a copy of the relevant notice of intention to apply for adjudication, a copy of the relevant payment claim and a copy of the payment response (if any) thereto.
(3)  The notice that an authorised nominating body is required to serve under section 13(4)(b) of the Act on the principal (if known) and the owner concerned that an adjudication application has been made shall contain the following particulars:
(a)the names and service addresses of the claimant and the respondent;
(b)the adjudication application reference number assigned by the authorised nominating body;
(c)the date of the adjudication application;
(d)the claimed amount;
(e)the response amount (if any); and
(f)a brief description of the payment claim dispute as contained in the adjudication application.
(4)  In this regulation, “notice of intention to apply for adjudication” means a notice by which a claimant is required under section 13(2) of the Act to notify a respondent of his intention to apply for adjudication of a payment claim dispute.
Adjudication responses
8.—(1)  Every adjudication response shall —
(a)refer to the relevant adjudication application by the adjudication application reference number assigned by the authorised nominating body;
(b)where the contract that is the subject of the payment claim dispute is a sub-contract, contain the date the main contract is made;
(c)contain details of the response amount (if any); and
(d)where the respondent intends to supplement the relevant payment response, contain the additional computations and justifications.
(2)  The notice that an authorised nominating body is required to serve under section 15(4)(b) of the Act on the principal (if known) and the owner concerned that an adjudication response has been lodged shall contain the following particulars:
(a)the names and service addresses of the claimant and the respondent;
(b)the adjudication application reference number assigned by the authorised nominating body;
(c)the date of the relevant adjudication application; and
(d)where the contract that is the subject of the payment claim dispute is a sub-contract, the date the main contract is made.
Adjudication determinations
9.—(1)  The notice that an authorised nominating body is required to serve under section 17(8)(b) of the Act on the principal (if known) and the owner concerned that an adjudication determination has been made shall contain the following particulars:
(a)the names and service addresses of the claimant and the respondent;
(b)the adjudication application reference number assigned by the authorised nominating body;
(c)the date of the relevant adjudication application;
(d)the claimed amount;
(e)the response amount (if any);
(f)the adjudicated amount; and
(g)the date on which the adjudicated amount is payable.
(2)  The notice that an authorised nominating body is required to serve under section 17(8)(b) of the Act on the principal (if known) and the owner concerned that an adjudication determination has been amended shall contain the following particulars:
(a)the names and service addresses of the claimant and the respondent;
(b)the adjudication application reference number assigned by the authorised nominating body;
(c)the date of the relevant adjudication application; and
(d)the particulars of the amendments made to the adjudication determination.
Adjudication review applications
10.—(1)  A respondent who is a party to an adjudication shall be entitled to lodge an application for the review of the determination of the adjudicator under section 18 of the Act if the adjudicated amount exceeds the relevant response amount by $100,000 or more.
(2)  Every adjudication review application shall —
(a)contain proof of payment of the adjudicated amount to the claimant pursuant to section 18(3) of the Act; and
(b)be accompanied by a copy of the adjudication determination that is the subject of the application.
(3)  An authorised nominating body shall, upon receipt of an adjudication review application —
(a)appoint one review adjudicator if the adjudicated amount exceeds the relevant response amount by $100,000 or more but less than $1 million; or
(b)appoint a panel of 3 review adjudicators if the adjudicated amount exceeds the relevant response amount by $1 million or more.
Eligibility criteria for adjudicators
11.—(1)  A person is eligible to be on the register of adjudicators established under section 28(4)(a) of the Act if —
(a)the person possesses such degree or diploma in architecture, building studies, engineering, environmental studies, law, planning, real estate or urban design, or such other qualification, as may be recognised by the authorised nominating body; and
(b)the person has working experience of at least 10 years in, or relating to, the building and construction industry in Singapore, and has successfully completed the pre-qualification assessment and training course conducted by the authorised nominating body.
(2)  For the purposes of section 29(2) of the Act, a person is not eligible to be an adjudicator in relation to a contract if the person is related to a party to the contract in the following manner:
(a)the person is an employee or a partner of the party, or where the party is a corporation, the person is a director or a shareholder of the corporation;
(b)the person is an employee, a director, a partner or a shareholder of any corporation which owns or is owned by the party;
(c)the person is a parent, spouse or sibling of the party; or
(d)the person has assisted the party to prepare any document for, or has provided any advice to, the party in relation to the contract.
(3)  In paragraph (2) —
“corporation” has the same meaning as in section 4(1) of the Companies Act (Cap. 50);
“parent” includes a step-parent or an adoptive parent;
“sibling” means a brother or sister, and includes a step-brother or step-sister or an adopted brother or sister.
Costs of adjudication proceedings
12.  For the purposes of section 30(1) of the Act —
(a)the fee payable to an authorised nominating body shall not exceed —
(i)$500 for each adjudication application; and
(ii)$1,000 for each adjudication review application; and
(b)the fee payable to an adjudicator (including a review adjudicator or a panel of review adjudicators) shall be computed on the basis of a rate not exceeding $2,000 per day or $250 per hour, subject to —
(i)where the claimed amount exceeds $20,000, a maximum of 10% of the claimed amount; or
(ii)in any other case, a maximum of $2,000.
[G.N. No. S 2/2005]