In exercise of the powers conferred by section 22 of the Housing Developers (Control and Licensing) Act, the Minister for National Development makes the following Rules:
PART 1
PRELIMINARY
Citation and commencement
1.—(1)  These Rules may be cited as the Housing Developers (Show Unit) Rules 2015 and, with the exception of rules 14(1)(c) and (f) and 15(1)(c) and (f), come into operation on 20 July 2015.
(2)  Rules 14(1)(c) and (f) and 15(1)(c) and (f) come into operation on 25 May 2015.
Definitions
2.  In these Rules, unless the context otherwise requires —
“approved building plan” means a building plan approved by the Commissioner of Building Control under section 5(3) or 5A(3) of the Building Control Act (Cap. 29);
“building plan” means a plan of any building works submitted to the Commissioner of Building Control for approval under section 5(1) or 5A(1) of the Building Control Act;
“Commissioner of Building Control” has the same meaning as in section 2(1) of the Building Control Act;
“depicted unit”, in relation to a building project, means the unit in the building project which is depicted by a show unit erected, set up or displayed by the licensed housing developer of the building project;
“location plan”, in relation to a building project, means a plan or model that shows the location of the building project and the surrounding roads, places, buildings and other landmarks;
“working day” means any day other than a Saturday, Sunday or public holiday.
Made on 7 May 2015.
BENNY LIM
Permanent Secretary,
Ministry of National Development,
Singapore.
[ND 202/1-57 Vol. 21; AG/LLRD/SL/130/2010/3 Vol. 1]
(To be presented to Parliament under section 22(5) of the Housing Developers (Control and Licensing) Act).